Stack demolition: timeline, road closures

February 19

Afternoon: Exclusion Zone fencing will start to be erected but full access will remain open

February 20

6am: Exclusion Zone closed to entering vehicles

7.30am: Police doorknock Exclusion Zone houses and ask residents to depart

8am: All Exclusion Zone homes have been visited

8am: Exclusion Zone closed to exiting vehicles

8.45-11am: Demolition takes place during this time, dependent on safety checks

After demolition: 15 minutes after demolition it is anticipated the all clear will be given via registered SMS numbers, www.stackinfo.com.au and lifting of road barriers.

Road closures

Fall of an icon: A map of the roads that will be closed

 ·      Darcy Road between the intersection of Old Port Road and the Darcy Road PKC entrance 

·      Military Road between Old Port Road and First Avenue

·      Wentworth Street east of number 164

·      Wentworth Lane near the intersection of Church Street

·      Allan Street north of Wentworth Street 

·      Fitzwilliam Street north of Wentworth Lane 

·      Church Street north of Wentworth Lane 

·      Military Lane north of number 17

·      Third Avenue north of number 16 

·      Second Avenue north of number 6 

·      Reservoir Street north of number 17 

·      Marne Street north of number 7 

·      Electrolytic Street

·      Reservoir Street Third Avenue Church Street